Progress Continues at Bioenergy Devco MD-FCA Facility in Jessup, MD

August 5, 2021 – The bioreactor structure, main process area building, with office area steel erection in process are located at the top of the image. Crews can be seen installing insulation on the pretank structure prior to pouring a concrete roof topping (pink insulation on rectangular structure). Two fermenter tanks can be seen with perimeter platform bracket supports and equipment installed, and piping well underway in one fermenter.

« »